Collaboration, work and institutions

1880s–1890

Forth Bridge: Hydraulic Tools and Erection

Study Arrol’s Forth Bridge erection work through hydraulic tools, changing utility lines and temporary loads, with evidence from the 1890 construction account.

Original explanatory diagram for Forth Bridge: Hydraulic Tools and Erection

The short answer

The Forth Bridge’s hydraulic riveting equipment required a supply system extending from its pressure-producing apparatus to machines on the rising structure. The ICE museum describes compressed water delivered up the towers and along the cantilevers, with pipework adjusted as construction progressed. This was an operating network within the construction site. It differed from the permanent bridge’s function of supporting trains. Studying that distinction makes Arrol’s contribution concrete: fabricating and erecting an immense steel structure required tools that could work where each new connection had to be made.

A worked comparison

What each part contributes

Use the specific distinctions developed in the study.

Original editorial comparison based on the inspected records.
Part or recordWhat it establishesWhy the distinction matters
Water-pressure linesDelivery to working toolsSupply and point of use are separate
RivetingForms a structural connectionRequires access and suitable support
Setting outAnticipates later movementDifferent from final unloaded position

How did power reach a riveter above the water?

The Forth Bridge’s hydraulic riveting equipment required a supply system extending from its pressure-producing apparatus to machines on the rising structure. The ICE museum describes compressed water delivered up the towers and along the cantilevers, with pipework adjusted as construction progressed. This was an operating network within the construction site. It differed from the permanent bridge’s function of supporting trains. Studying that distinction makes Arrol’s contribution concrete: fabricating and erecting an immense steel structure required tools that could work where each new connection had to be made.

Sources for this section: [2] · [3]

Water, compressed air and oil were separate supplies

Westhofen’s contemporary page describes separate pipes for the water working hydraulic riveters, compressed air and oil for furnaces. It also describes oil descending from a tank by gravity. Those lines served different equipment and cannot be treated as interchangeable versions of hydraulic power. The distinction helps explain the site as an operating workplace: a riveting tool needed its pressure supply, while a furnace needed fuel. Extending steelwork therefore created utility and maintenance tasks as well as a new place to fasten another structural member.

Sources for this section: [3]

The unfinished bridge carried construction equipment too

Westhofen’s 1890 account describes cranes, temporary girders, winches, boilers, furnaces, ropes and staging supported on the cantilevers. Those loads existed before the eventual railway service. Erection planning therefore could not consider only the weight of the final structural members. Equipment made assembly possible while also adding weight and requiring working space. The source’s explanation shows a genuine construction interface: the partially completed structure supported the means by which its next sections were installed, and the temporary arrangement changed as the work advanced.

Sources for this section: [3]

Position during erection anticipated later deflection

The same contemporary account explains that cantilever sections were set higher than the desired final position to allow for deflection as further members were added. The final unloaded camber and the setting-out allowance were related but different quantities. This was not a decorative upward curve added after construction. It was a sequencing decision based on expected movement of the growing structure. Together with the hydraulic supply, it illustrates why the construction record adds something beyond the consulting designers’ names or the date on which the permanent railway opened.

Sources for this section: [3]

Construction-interface exercise and checked answer

A fictional contractor has a working hydraulic riveter and adequate pressure at ground level, but no completed pipe connection to the next work position. Is the machine ready to form that joint? No: supply must reach the point of use, and the machine and crew need suitable access and support. A second question asks whether setting a member at its intended final level necessarily accounts for the deflection caused by later construction. Again, no. The checked answer considers the changing load sequence. These examples identify practical dependencies without inventing a measured pressure, erection load or deflection for Arrol’s actual equipment.

Sources for this section: [2] · [3]

Continue the chronology

Biography context

Explore United Kingdom through connected lives

Connected biographies

People and wider context

United KingdomBusiness

1839–1913

William Arrol

engineering contractor and structural-steel manufacturerWilliam Arrol was a engineering contractor and structural-steel manufacturer, known for bridge construction, erection equipment and hydraulic riveting.Read biography

Quick answers

Common questions

Was all equipment carried by the Forth cantilevers part of the finished railway?
No. The contemporary account describes temporary cranes, furnaces, staging and other equipment needed during construction.

Primary and institutional sources

How this history was checked

Read the cited original records, institutional accounts and later interpretations. The comparison and exercise explain the specific evidence used in this study. This article was reviewed on 8 November 2026.

  1. William Cawthorne Unwin, Dictionary of National Biography, 1927 supplementArrol, William
  2. Institution of Civil Engineers Scotland MuseumHydraulic riveting machine, circa 1887
  3. Wilhelm Westhofen, Engineering, 1890; Wikisource transcriptionThe Forth Bridge, printed page 55