Thai history · Urban rail extensions

2017–2020

How Bangkok’s Blue Line Extensions Met at Tha Phra

Follow the Blue Line beyond its original termini through the 2019 and 2020 openings, and see why its two extensions meet at Tha Phra.

The 2019 line from Hua Lamphong and the 2020 line from Bang Sue reach Tha Phra by separate routes
29 Sep 2019
Hua Lamphong–Bang Khae section enters service
30 Mar 2020
Bang Sue–Tha Phra section enters service
Tha Phra
Junction of the two extensions

The short answer

Bangkok’s original underground Blue Line ended at Hua Lamphong and Bang Sue. Its later extensions took different routes across the Chao Phraya and met at Tha Phra. The operating dates in 2019 and 2020 explain how a line originally built between two terminals gained its loop and a western branch.

Compare the records

How the two extensions differ

Both routes reach Tha Phra, but their starting points and river crossings are different.

Following the two approaches to Tha Phra
SectionRiver and alignmentService milestone
Hua Lamphong through Tha Phra toward Lak SongRuns through the old city and tunnels beneath the Chao Phraya on its way westSeptember 2019.
Bang Sue through Tao Poon to Tha PhraRuns via the Purple Line junction and crosses the river on the northern sideMarch 2020.

Chronology

A timeline of the turning points

  1. Operating arrangements for the expanded line

    MRTA and BEM signed agreements covering the wider network.

  2. Western section enters service

    The extension beyond Hua Lamphong connected the old city with the route to Lak Song.

  3. Northern and western connection enters service

    The section from Bang Sue through Tao Poon reached Tha Phra.

  4. Extension ceremony

    MRTA records a later ceremony for the expanded line at Sanam Chai.

From Hua Lamphong toward Lak Song

MRTA’s description follows the extension through Wat Mangkon and Sanam Chai before it goes under the Chao Phraya. The route reaches Itsaraphap and Tha Phra, then continues toward Bang Khae and Lak Song. This route is the one to follow when reading about underground stations in the old city or the branch continuing past Tha Phra.

Sources for this section: [1] · [3]

From Bang Sue through Tao Poon

The other extension begins from the Bang Sue end of the original line and connects with the Purple Line at Tao Poon. It crosses the river farther north and approaches Tha Phra along the west side. Follow both sections on a dated map to see why Tha Phra can be both a point on a westbound journey and the end of a route that has passed around the loop.

Sources for this section: [1] · [3]

Why an opening ceremony can follow service

MRTA lists 29 September 2019 and 30 March 2020 as the service dates of the respective sections. It separately records the ceremony of 14 November 2020. These dates identify when trains began using each extension and when the wider project received its formal opening. Earlier station lists for the original 2004 line describe a different operating network.

Sources for this section: [1] · [2]

Continue the chronology

Connected biographies

People connected to this history

Quick answers

Common questions

When did the Blue Line extensions start service?
MRTA gives 29 September 2019 for the western extension and 30 March 2020 for the section from Bang Sue to Tha Phra.
Where do the extensions meet?
The two routes meet at Tha Phra on the west side of the Chao Phraya.

Primary and institutional sources

How this history was checked

Dates, legal milestones and historical claims are checked against the official and institutional records below. This article was reviewed on 19 November 2026.

  1. Mass Rapid Transit Authority of ThailandBlue Line original route, extension routes and start dates
  2. Mass Rapid Transit Authority of ThailandBlue Line extension ceremony, November 2020
  3. Japan International Cooperation AgencyThailand–Japan cooperation on Bangkok mass rapid transit