Malaysia energy and social history

1998–2014

Bakun Dam: When Power Began and When Families Moved

Compare Bakun Dam’s 2011–2014 commissioning with the 1998 relocation to Sungai Asap, using operator records and research with displaced communities.

Bakun Dam and construction works in Sarawak before commissioning
1998
Relocation to Sungai Asap
2011
First units commissioned
2014
Plant fully operational

The short answer

Sarawak relocated 15 longhouse communities in 1998 from the area that would become the Bakun reservoir. Bakun’s generating units began commissioning in 2011, and the plant was fully operational in 2014. Reading both timelines shows why the dam’s consequences for nearby communities began years before it produced electricity.

Reading the project records

Land, livelihood and electricity

Each kind of record answers a different question about the same development.

Evidence for Bakun’s relocation and power milestones
RecordWhat it establishesWhat it does not measure by itself
Resettlement assessmentWhere residents were moved and what the project countedChanges in all households’ access to customary resources
Fieldwork with residentsHow some families described changes in land use and livelihoodsA numerical outcome that applies to every family
Plant commissioning recordWhen electricity capacity entered serviceWhether livelihood changes were resolved

Chronology

A timeline of the turning points

  1. Government moves longhouse communities

    The principal resettlement scheme is at Sungai Asap. Some households make other arrangements.

  2. Generating units begin commissioning

    The operator identifies the first year of unit commissioning on the Balui River.

  3. Power plant fully operational

    Sarawak Energy’s project records mark the end of staged commissioning.

  4. Studies revisit resettlement

    Researchers and the operator examine effects on land use, livelihoods and communities.

How relocation preceded generation

Sarawak Energy’s assessment dates the relocation of 15 longhouse communities to 1998. It also records that some households declined to join the scheme and moved independently. The census figures describe households in the affected area, which is a different count from households that took up the same resettlement offer.

The generating timeline starts over a decade later. The first units were commissioned in 2011 and the project became fully operational in 2014. Those dates answer an engineering question, while 1998 answers when the relocation occurred.

Sources for this section: [1] · [2]

What was lost or replaced

Researchers who interviewed displaced communities describe changes in access to forest resources, customary land and the location of agricultural plots. A home and a farming allotment address part of a household’s needs. A move can also change the journey to land, rivers and places used jointly by a community.

The research adds evidence that cannot be read from the number of houses or from the capacity of the turbines. Its interviews document how participants experienced the changes. Individual circumstances varied, especially where families moved outside the main scheme.

Sources for this section: [3] · [1]

Why the operating project still has a social record

Sarawak Energy’s Indigenous Peoples’ Plan inception report identifies communities to consult about ongoing effects and what measures could be taken. A commissioned plant can generate power while institutions continue to address consequences of its development.

Comparing the operator’s documents with fieldwork also helps readers follow changes across time. The operator records how the programme was administered. The interviews provide a view of how land access and household livelihoods looked from some of the communities affected.

Sources for this section: [2] · [3]

Continue the chronology

Connected biographies

People connected to this history

Quick answers

Common questions

When did Bakun begin generating power?
Sarawak Energy dates initial unit commissioning to 2011 and full operation to 2014.
Where were communities relocated for the Bakun project?
Sungai Asap was the main resettlement area. The operator’s assessment records households that moved independently as well.

Primary and institutional sources

How this history was checked

Dates, legal milestones and historical claims are checked against the official and institutional records below. This article was reviewed on 19 November 2026.

  1. Sarawak EnergyBakun hydropower preliminary assessment: displacement and resettlement
  2. Sarawak EnergyInception report for Bakun Indigenous Peoples’ Plan
  3. Land, primary fieldwork studyCredibility and the Social Function of Property: a study of displaced communities in Malaysia